|
|
|||||||||
By Murray Wiseman
(extracted from Chapter 16 of “Reliability-centered Knowledge”)
Improvement
concepts such as “the maintenance dashboard”, “key
performance indicators”, and “benchmarking of the best of breed ” resonate in
the physical asset management community. They are the stock in trade of the
maintenance management consultant. A far-sighted vision and a well-conceived
strategy followed by a detailed implementation effort, will, we expect,
transform the maintenance function into an ordered and controllable process.
With minor
variations, two schools of thought
dominate the scores of philosophies that contend in the maintenance improvement
marketplace. The symbolic “pyramid of excellence” (Figure 1),
and the metaphoric “RCM house” (Figure 2) convey their
respective, and somewhat conflicting, paths to “world class physical asset
management”.
|
Figure 1 The Pyramid of Excellence[1] |
Figure 2 The RCM "House"[2] |
Order, rather than content, differentiate the two approaches. The former initializes
its improvement cycle by establishing a suitable maintenance infrastructure
(tiers one and two at the base of the pyramid) . The
latter insists that we retain (for the present) our existing systems and
structures, but, that we begin (the improvement process) by analyzing
each significant physical asset’s functions, its failures, failure causes,
effects, and consequences. Doing so will determine the appropriate maintenance
requirements – the foundation (of the house of Figure 2).
Proponents, of the “Pyramid of Excellence”, emphasize culture change as
an explicit management process. The RCM camp contends that maintenance culture
will adapt naturally with systematic RCM education and implementation.
The former devotes attention to
effective planning and scheduling, while the latter focuses on
developing, through RCM analysis, the proactive cyclic tasks (TBM and CBM) of
the maintenance plan[3].
Summarizing, students
of the “Pyramid” school defer reliability-centered maintenance (RCM)
analysis to a future time by placing it up on the third tier. They see the
processes (such as data management and planning) on tier 2 as pre-requisites
for reliability analysis (RCM).
Advocates of the alternative point of view (the “House”),
consign “systems” to the roof (the last element to be erected in
an improvement plan), while positioning RCM analysis as the foundation.
In this chapter we review software products such as Strategy Manager™ [4],
Real-Time Production Intelligence™[5],
and Real-Time Production Management™[6]
that seek to unify the two[7]
approaches.
Occasionally,
corporate management elects to
perform a “maintenance assessment” at one or more of its sites. Independent
consultants conduct the audit, principally, by interviewing a cross-section of
maintenance and operating staff, and, by reviewing various CMMS reports and
budget documents. Sometimes the consultants map out flow diagrams that trace
the business processes used in the maintenance department. Occasionally a
consultant will observe and take notes during regular maintenance meetings. In
all cases, to complete the audit, the consultant team delivers a final report
evaluating the maintenance department’s performance relative to a set of benchmarks
that characterize the “best” organizations. The report recommends projects and
changes that will narrow the “gaps” to achieving excellence in each of the
(ten) areas of Figure 1. The consultants propose a
project priority sequence based on the value of the improvement and its ease of
implementation.
New software enabled
methodologies extend the reach of the occasional maintenance audit
by offering continuous day-to-day performance visibility and control. To
accomplish this function they integrate, (using O&MOpen[8]
standards) with the CMMS, process computers, and other plant systems.
Figure 3 Physical Asset Management input, outputs, and control
Figure
3 illustrates the two feedback “control” loops of physical asset management.
Their ultimate output achieves the corporate vision. Each feedback arrow
represents a management function:
Arrow 3 represents the
way that maintenance policy relates to the KPIs, and arrow 4 represents how the
actual KPI’s achieve corporate vision. The physical asset manager strives to
discover the intricate relationships governing how policy impacts KPIs. And,
secondly, he seeks to know how achievement of the KPI targets will impact the
balance sheet and the corporation’s societal responsibilities of
custodianship. We might express the steps to world class performance as:
Note that the center
block of Figure 3 specifies both KPIs and Age
Exploration[9]. KPIs
often summarize the results of a maintenance policy. They seldom direct
us to specific policy changes regarding individual assets. On the
other hand, age exploration analyses (for example, Pareto analyses) focus our
attention on individual significant items whose collective performance governs
the KPIs.
The foregoing implies
that our maintenance management system (CMMS) must embody reliability-centered
information (as outlined in Chapters 1, 2, and 3). Specifically, for each
significant item, the five reliability-centered knowledge
elements:
will populate the
database upon which the analyses will be performed. Furthermore, using our system,
we establish the relationship between the significant consequences of failure (knowledge element 5) and the
KPIs that achieve the corporate vision. In practical terms, we use the performance
management system to classify each incident (maintenance work order,
or production log item) involving downtime, speed loss, or quality loss, as one
of 11 to 19 of Table 2. Additionally, we document
the five RCM knowledge elements that
characterize each incident (see Figure
4).
Effectiveness KPIs
classify productivity losses as: Downtime, Speed, and Quality
losses.
Table 1
|
Theoretical production
time 1 |
|||||||||
|
Valuable operating time 8 |
Losses |
||||||||
|
Quality losses |
Speed losses |
Downtime losses |
|||||||
|
MM |
P |
E |
MM |
P |
E |
MM |
P |
E |
|
Table 2 Model 1 Production Economy
|
Theoretical production time 1 |
|
|||||||||||
|
Available production time 2 |
External losses 3 Unplanned: 1.
shortage of personnel 2.
shortage of materials (quantity, quality 3.
Environmental deals Planned: 1.
Modification, major mtce 2.
Limited need 3. Social (policy
not to produce weekends, holidays, etc |
|
||||||||||
|
Gross operating time 4 |
Downtime 5 |
|
||||||||||
|
Net operating time 6 |
Speed losses 7 |
|
||||||||||
|
Valuable operating time 8 |
Quality losses 9 |
|
||||||||||
|
MM 14 |
P 15 |
MM 16 |
P 17 |
MM 18 |
P 19 |
|||||||
|
Quality 11 |
Speed 12 |
Down time 13 |
||||||||||
|
Technical losses 10 |
||||||||||||
MM=machine malfunctioning, P=process
Table 3 Model
2 Dupont (“planned production time” or “six big losses”) model
|
Theoretical production time 1 |
|
|||||||
|
Planned production time = Available production time 2 |
Planned losses 3 -
Authorized breaks (pauses) during the working day -
Not working during weekends -
Scheduled stoppages for product changes -
Modifications and improvements to equipment (work financed under
investments) -
Decreased production time due to lack of demand for the product -
Planned maintenance work (inspections, preventive maintenance,
improvements) -
Problems in production planning -
Saturation of machines (upstream and downstream) -
Authorized shop floor meetings -
Classroom or ‘on the job’ training sessions for operators -
External power cuts -
Lack of raw material |
|||||||
|
Gross operating time 4 |
Downtime losses 5 |
|||||||
|
Net operating time 6 |
Speed losses 7 |
Setup and adjustment Big loss 5 |
Equipment failure Big loss 6 |
|||||
|
|
||||||||
|
Valuable operating time 8 |
Quality losses 9 |
Reduced speed Big loss 3 |
Idling and minor stops Big loss 4 |
|||||
|
Reduced yield from startup Big loss 1 |
Defects in process Big loss 2 |
|||||||
Of the two models
(Production economy vs. Dupont analysis) Model 1 is more generally applicable.
It is easier to allocate incidents to their causes (MM, P, or E) than to the
“six big losses” of Table 3.
External losses are losses that cannot be altered by the
production or maintenance team. Planned down time losses are down time
losses that were planned. Note that planned down time losses (of Model
2) are specifically down time losses, whereas external losses (of Model
1), can be speed, quality, and downtime losses. For instance, speed losses
because of environmental deals are external losses but are not planned
down time losses. Similarly, quality losses that are caused by the raw
materials are external losses but are not down time. Hence Model
1 discriminates more easily between losses controllable by maintenance (and
operations) and those that are outside of its control, than does Model 2.
Furthermore external
losses are not always planned. For instance, an external power cut or lack of
raw materials is an external loss, but is not a planned down time loss. Hence,
‘available production time’ is different in the two models. Therefore the KPIs
calculated in Table 4 will have different values
depending on whether Model 1 or Model 2 is used. However, by leveraging the
next generation of management software, we may,if required, convert the five
RCM knowledge elements associated with each incident (from Model 1) into the
six big losses (of Model 2).
Table 4
Productivity KPIs
|
Planning factor, PF |
|
|||||||||||||
|
Availability factor,
A |
|
|||||||||||||
|
Performance factor,
P |
|
|||||||||||||
|
Quality factor, Q |
|
|||||||||||||
|
Valuable operating
time |
||||||||||||||
|
OEE |
|
|||||||||||||
|
Total OEE |
(=OEExPF) |
|||||||||||||
|
Theoretical cycle
time |
Determine by a
neutral instance. Consult both production and maintenance. Do not include
external losses. (imposed by legal/hygiene) |
Time units /part
|
Table 5
Example: (using the Production Economy model definitions)
|
January to September |
273 days = 6552
hours |
|
|
Weekends 78 days, holidays
7 days, vacation 11 days = 96 days |
|
273-96=177 |
|
No production on
night shift |
|
177 x 2 x 8 = 2816
hours |
|
Breaks 1 hour /day |
|
2816-177=2640 |
|
Lack of
personnel/raw material estimated at 5% |
.95x2640=2508 |
|
|
Downtime (unplanned)
recorded was 551 hours |
551 |
There are four
production lines whose reference throughput and approved product for the period
under study are given in Table 6.
Table 6
|
|
Reference throughput
kg/h |
No. approved kg |
Valuable operating
time 8
|
|
Line 1 |
1500 |
720000 |
480 |
|
Line 2 |
750 |
334000 |
445 |
|
Line 3 |
900 |
160000 |
178 |
|
Line 4 |
680 |
36000 |
53 |
|
Total valuable
operating time |
1156 |
||
|
OEE |
1156/2508 |
|
|
PF |
2508/6552 |
|
|
Total OEE |
1156/6552 |
|
|
Availability |
(2508-551)/2508 |
Mastery of the processes 1, 2, 3, and 4 of Figure 3 imposes the greatest challenge upon maintenance performance management. The next generation of maintenance performance management software will dissect every KPI into its constituant incidences and knowledge elements (as in Figure 4).
Figure 4 A Performance Management system drills down from the KPI (for example, Quality Loss) to invoke analysis procedures that guide the physical asset manager to continuous policy improvement
Figure 4 illustrates that historical data (contained in plant systems) fuel reliability analyses such as Pareto, age-reliability relationships, and optimal CBM decision graphs[11]. Those methodologies steer us towards improved maintenance policies. The CMMS, the control system historian, CBM databases, and other plant systems feed information to the performance management system. The performance management system, in the hands of the physical asset manager, outputs continually improving physical asset management policies. Today, the maintenance world hovers at the threshold of bridging two remaining gaps that impede “excellence” in asset performance management. They are:
1. CMMS workorders do not yet record reliability-centered knowledge. (Chapters 1-3)
2. The RCM knowledge base is not yet fully integrated with the CMMS, process historian, and CBM databases (Chapter 15)
With these final
capabilities in hand, we may anticipate rewarding times ahead for physical
asset management.
Do you have any comments on this article? If so, send them to murray@omdec.com
[1] From Uptime, John Dixon Campbell, Productivity Press, 1995
[2] From the RCM II Practitioner’s course, John Moubray 1999
[3] Along with the defaults “no scheduled maintenance” and redesign.
[4] Available from DEI Group (www.dei-group.com)
[5] Available from ABB (www.abb.com)
[6] Available from OSISoft (www.osisoft.com)
[7] systems first or reliability first
[8] See www.mimosa.org and the article EXAKT and MIMOSA
[9] A broad category of methods of analysis of failure and maintenance data. The analyses target ways to improve current proactive maintenance policies on significant items in order to improve reliability and/or lower cost. See Chapter 3.
[10] Bert Mijten, Real-Time Production Intelligence, ABB Review, Feb 2004
[11] These may be called age-reliability-significant factor relationships
|